1 CFR §601.4
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)A Federal Agency applicant shall serve as the Lead Agency and prepare an EA or an EIS for:
- (1)An application that requires Commission approval; and
- (2)An application for action on a master plan that includes future projects that require Commission approval; provided that:
- (i)The applicant intends to submit individual projects covered by the master plan to the Commission within five years of the date of Commission action on the master plan; and
- (ii)The applicant intends to use the master plan EA or EIS to satisfy its NEPA obligation for specific projects referenced in the master plan.
- (b)NCPC shall serve as Lead Agency and prepare an EA or an EIS for:
- (1)An application submitted by a Non-Federal Agency that requires Commission approval;
- (2)An application submitted by a Non-Federal Agency for action on a master plan that includes future projects that require Commission approval; provided that:
- (i)The Non-Federal Agency applicant intends to submit individual projects covered by the master plan to the Commission within five years of the date of Commission action on the master plan; and
- (ii)The Non-Federal Agency applicant intends to use the master plan EA or EIS to satisfy its NEPA obligation for a specific project referenced in the master plan; and
- (3)An application for approval of land acquisitions undertaken pursuant to 40 U.S.C. 8731-8732.