10 CFR §60.140
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)The performance confirmation program shall provide data which indicates, where practicable, whether:
- (1)Actual subsurface conditions encountered and changes in those conditions during construction and waste emplacement operations are within the limits assumed in the licensing review; and
- (2)Natural and engineered systems and components required for repository operation, or which are designed or assumed to operate as barriers after permanent closure, are functioning as intended and anticipated.
- (b)The program shall have been started during site characterization and it will continue until permanent closure.
- (c)The program shall include in situ monitoring, laboratory and field testing, and in situ experiments, as may be appropriate to accomplish the objective as stated above.
- (d)The program shall be implemented so that:
- (1)It does not adversely affect the ability of the natural and engineered elements of the geologic repository to meet the performance objectives.
- (2)It provides baseline information and analysis of that information on those parameters and natural processes pertaining to the geologic setting that may be changed by site characterization, construction, and operational activities.
- (3)It monitors and analyzes changes from the baseline condition of parameters that could affect the performance of a geologic repository.
- (4)It provides an established plan for feedback and analysis of data, and implementation of appropriate action.