10 CFR §830.122
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
The QAP must address the following management, performance, and assessment criteria:
Establish and implement processes to ensure that approved suppliers continue to provide acceptable items and services.
- (a)Criterion 1—Management/Program.
- (b)Criterion 2—Management/Personnel Training and Qualification.
- (c)Criterion 3—Management/Quality Improvement.
- (1)Establish and implement processes to detect and prevent quality problems.
- (2)Identify, control, and correct items, services, and processes that do not meet established requirements.
- (3)Identify the causes of problems and work to prevent recurrence as a part of correcting the problem.
- (4)Review item characteristics, process implementation, and other quality-related information to identify items, services, and processes needing improvement.
- (d)Criterion 4—Management/Documents and Records.
- (e)Criterion 5—Performance/Work Processes.
- (1)Perform work consistent with technical standards, administrative controls, and other hazard controls adopted to meet regulatory or contract requirements, using approved instructions, procedures, or other appropriate means.
- (2)Identify and control items to ensure their proper use.
- (3)Maintain items to prevent their damage, loss, or deterioration.
- (4)Calibrate and maintain equipment used for process monitoring or data collection.
- (f)Criterion 6—Performance/Design.
- (1)Design items and processes using sound engineering/scientific principles and appropriate standards.
- (2)Incorporate applicable requirements and design bases in design work and design changes.
- (3)Identify and control design interfaces.
- (4)Verify or validate the adequacy of design products using individuals or groups other than those who performed the work.
- (5)Verify or validate work before approval and implementation of the design.
- (g)Criterion 7—Performance/Procurement.
- (h)Criterion 8—Performance/Inspection and Acceptance Testing.
- (1)Inspect and test specified items, services, and processes using established acceptance and performance criteria.
- (2)Calibrate and maintain equipment used for inspections and tests.
- (i)Criterion 9—Assessment/Management Assessment. Ensure managers assess their management processes and identify and correct problems that hinder the organization from achieving its objectives.
- (j)Criterion 10—Assessment/Independent Assessment.
- (1)Plan and conduct independent assessments to measure item and service quality, to measure the adequacy of work performance, and to promote improvement.
- (2)Establish sufficient authority, and freedom from line management, for the group performing independent assessments.
- (3)Ensure persons who perform independent assessments are technically qualified and knowledgeable in the areas to be assessed.