- (a)Preparation and submission of initial CBDPP to DOE.
- (1)The responsible employer at a DOE facility must ensure that a CBDPP is prepared for the facility and submitted to the appropriate Head of DOE Field Element before beginning beryllium activities, but no later than April 6, 2000 of this part.
- (2)If the CBDPP has separate sections addressing the activities of multiple contractors at the facility, the Head of DOE Field Element will designate a single DOE contractor to review and approve the sections prepared by other contractors, so that a single consolidated CBDPP for the facility is submitted to the Head of DOE Field Element for review and approval.
- (b)DOE review and approval. The appropriate Head of DOE Field Element must review and approve the CBDPP.
- (1)The initial CBDPP and any updates are deemed approved 90 days after submission if they are not specifically approved or rejected by DOE earlier.
- (2)The responsible employer must furnish a copy of the approved CBDPP, upon request, to the DOE Director, Office of Environment, Health, Safety and Security or designee, DOE program offices, and affected workers or their designated representatives.
- (c)Update. The responsible employer must submit an update of the CBDPP to the appropriate Head of DOE Field Element for review and approval whenever a significant change or significant addition to the CBDPP is made or a change in contractors occurs. The Head of DOE Field Element must review the CBDPP at least annually and, if necessary, require the responsible employer to update the CBDPP.
- (d)Labor Organizations. If a responsible employer employs or supervises beryllium-associated workers who are represented for collective bargaining by a labor organization, the responsible employer must: