10 CFR §903.13
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)The Administrator shall give Notice that Proposed Rates have been prepared and are under consideration. The Notice shall include:
- (1)The Proposed Rates;
- (2)An explanation of the need for and derivation of the Proposed Rates;
- (3)The locations at which data, studies, reports, or other documents used in developing the Proposed Rates are available for inspection and/or copying;
- (4)The dates, times, and locations of any initially scheduled public forums; and
- (5)Address to which written comments relative to the Proposed Rates and requests to be informed of FERC actions concerning the rates may be submitted.
- (b)Upon request, customers of the power system and other interested persons will be provided with copies of the principal documents used in developing the Proposed Rates.