- (a)Airport development. Except as provided in paragraphs (b) and (c) of this section, the following is the United States share of the allowable cost of an airport development project approved for the specified year:
- (1)90 percent in the case of grants made from funds for fiscal years 1976, 1977, and 1978, and grants from funds for fiscal year 1980 made after February 17, 1980, for—
- (i)Each air carrier airport, other than a commuter service airport, which enplanes less than one quarter of one percent of the total annual passengers enplaned as determined for purposes of making the latest annual apportionment under section 15(a)(3) of the AADA;
- (ii)Each commuter service airport; and
- (iii)Each general aviation or reliever airport.
- (2)80 percent in the case of grants made from funds for fiscal year 1979 and grants from funds for fiscal year 1980 made before February 18, 1980, for the airports specified in paragraph (a)(1) of this section.
- (3)75 percent in the case of grants made from funds for fiscal years 1976 through 1980 for airports other than those specified in paragraph (a)(1) of this section.
- (1)90 percent in the case of grants made from funds for fiscal years 1976, 1977, and 1978, and grants from funds for fiscal year 1980 made after February 17, 1980, for—
- (b)In a State in which the unappropriated and unreserved public lands and nontaxable Indian lands, both individual and tribal, are more than five percent of the total land in that State, the United States' share under paragraph (a) of this section—
- (c)In the case of terminal development, the United States share shall be 50 percent.
- (d)Airport planning. The United States share of the allowable project costs of an airport planning project shall be—