19 CFR Annex VIII-B to Part 351

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
Day 1EventRegulation
0 daysInitiation351.218(c).
15 daysFiling of Notice of Intent to Participate by domestic interested parties351.218(d)(1)(i) (not later than 15 days after the date of publication of the Notice of Initiation).
30 daysFiling of Statement of Waiver by respondent interested parties351.218(d)(2)(i) (not later than 30 days after the date of publication of the Notice of Initiation).
30 daysFiling of a complete substantive response to the Notice of Initiation by all interested parties and industrial users and consumers351.218(d)(3)(i) and 351.218(d)(3)(vi) (not later than 30 days after the date of publication of the Notice of Initiation).
35 daysFiling of rebuttal to substantive response to the Notice of Initiation351.218(d)(4) (not later than 5 days after the substantive response is filed with the Department).
50 daysWritten notification to the ITC that respondent interested parties provided inadequate response to the Notice of Initiation351.218(e)(1)(ii)(C)(1) (normally not later than 50 days after the date of publication of the Notice of Initiation).
70 daysComments on adequacy of response and appropriateness of expedited sunset review351.309(e)(ii) (not later than 70 days after the date of publication of the Notice of Initiation).
120 daysFinal results of expedited sunset review where respondent interested parties, and foreign governments, provide inadequate response to the Notice of Initiation351.218(e)(1)(ii)(B) and 351.218(e)(1)(ii)(C)(2) (not later than 120 days after the date of publication of the Notice of Initiation).

1 Indicates the number of days from the date of publication of the Notice of Initiation. Most of the deadlines shown here are approximate. The actual deadline in any particular segment of a proceeding may depend on the date of an earlier event or be established by the Secretary.

[89 FR 103637, Dec. 19, 2024]