21 CFR §507.120
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)The receiving facility must approve suppliers in accordance with the requirements of § 507.110(d), and document that approval, before receiving raw materials and other ingredients received from those suppliers;
- (b)
- (1)Written procedures for receiving raw materials and other ingredients must be established and followed;
- (2)The written procedures for receiving raw materials and other ingredients must ensure that raw materials and other ingredients are received only from approved suppliers (or, when necessary and appropriate, on a temporary basis from unapproved suppliers whose raw materials or other ingredients are subjected to adequate verification activities before acceptance for use); and
- (3)Use of the written procedures for receiving raw materials and other ingredients must be documented.