- (a)Authorization to proceed with preliminary engineering and acquisition of rights-of-way shall be issued in the same manner as for regularly financed Federal-aid projects.
- (b)Authorization of physical construction shall be given in the same manner as for regularly financed Federal-aid projects. The total cost and Federal funds required, including interest, shall be indicated in the plans, specifications, and estimates.
- (c)Projects subject to the reimbursable schedule shall be identified as an “E” project when the SHA is authorized to proceed with all or any phase of the work.
- (d)Concurrence in the award of contracts shall be given.