23 CFR §661.27
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)A complete application package for construction consists of the following:
- (1)A copy of the approved PS&E;
- (2)The certification checklist;
- (3)NBI data;
- (4)The TTP TIP;
- (5)All environmental and archeological clearances and complete grants of public rights-of-way that must be acquired prior to submittal of the construction application package; and
- (6)An acknowledgment by the Tribe of the project specific funding requirements and that any excess funds will be returned to FHWA for further distribution.
- (b)For non-BIA/non-Tribally owned TTF bridges, the application package must also include a copy of a letter from the bridge's owner approving the project and its PS&E and a Tribal resolution supporting the project.
- (c)Incomplete application packages will be disapproved and returned for revision and resubmission along with an explanation providing the reason for disapproval.
- (d)The TTF bridge projects for construction will be placed in the queue and determined as eligible for funding after receipt by FHWA of a complete application package.
- (e)Funding for the approved eligible projects in the queues will be made available to the Tribes, under a TTP Program Agreement between FHWA and a Tribal government, or the Secretary of the Interior upon availability of program funding at FHWA.