24 CFR §248.219
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Not later than 180 days after initial receipt of a plan of action, or within such longer period as the owner requests, the Commissioner shall notify the owner in writing whether the plan of action, including any revisions, is approved.
- (b)If approval is withheld, the notice will—
- (1)Describe the reasons for withholding approval, including prolonged delay by the owner in submitting a revised plan of action;
- (2)Describe the actions that could be taken to meet the criteria for approval; and
- (3)Afford the owner a reasonable opportunity to revise the plan of action and seek approval.