- (a)The following activities shall be conducted for all properties to which this subpart is applicable:
- (b)Occupancy shall not be permitted until all required paint stabilization is complete and clearance is achieved.
- (c)If paint stabilization and clearance are not completed before the closing of the sale, the Department shall assure that paint stabilization and clearance are carried out pursuant to subpart R of this part by the purchaser before occupancy.