24 CFR §401.100
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)What are the requirements for eligibility? To be eligible for a Restructuring Plan under this part, a project must:
- (1)Have a mortgage insured or held by HUD;
- (2)Be covered in whole or in part by a contract for project-based assistance under—
- (i)The new construction or substantial rehabilitation program under section 8(b)(2) of the U.S. Housing Act of 1937 as in effect before October 1, 1983;
- (ii)The property disposition program under section 8(b) of the U.S. Housing Act of 1937;
- (iii)The moderate rehabilitation program under section 8(e)(2) of the United States Housing Act of 1937;
- (iv)The loan management assistance program under section 8 of the United States Housing Act of 1937;
- (v)Section 23 of the United States Housing Act of 1937 as in effect before January 1, 1975;
- (vi)The rent supplement program under section 101 of the Housing and Urban Development Act of 1965;
- (vii)Section 8 of the United States Housing Act of 1937, following conversion from assistance under Section 101 of the Housing and Urban Development Act of 1965; or
- (viii)Section 8 of the U.S. Housing Act of 1937 as renewed under section 524 of MAHRA;
- (3)Have current gross potential rent for the project-based assisted units that exceeds the gross potential rent for the project-based assisted units using comparable market rents;
- (4)Have a first mortgage that has not previously been restructured under this part or under HUD's Portfolio Reengineering demonstration authority as defined in § 402.2(c) of this chapter;
- (5)Not be a project that is described in section 514(h) of MAHRA; and
- (6)Otherwise meet the definition of “eligible multifamily housing project” in section 512(2) of MAHRA or meet the following three criteria:
- (i)The project is assisted pursuant to a contract for Section 8 assistance renewed under section 524 of MAHRA;
- (ii)It has an owner that consents for the project to be treated as eligible; and
- (iii)At the time of its initial renewal under section 524, it met the requirements of section 512(2)(A), (B), and (C) of MAHRA.
- (b)When is eligibility determined? Eligibility for a Restructuring Plan under paragraph (a) of this section is determined by the status of a project on the earlier of the termination or expiration date of the project-based assistance contract, which includes a contract renewed under section 524 of MAHRA, or the date of the owner's request to HUD for a Restructuring Plan. Eligibility is not affected by a subsequent change in status, such as contract extension under § 401.600 or part 402 of this chapter.