- (a)Initial evaluation. The owner must evaluate the physical condition of the project and provide the following information to the PAE in a form acceptable to the PAE:
- (1)All work items required to bring the project to the standard in § 401.452, including any work items needed to ensure compliance with applicable requirements of part 8 of this title concerning accessibility to persons with disabilities;
- (2)The capital repair or replacement items that will be necessary to maintain the long-term physical integrity of the property;
- (3)A plan for funding the rehabilitation work included in paragraph (a)(1) of this section, which work must be completed in a timely manner after closing the restructuring transaction, that identifies the source of the required owner contribution of non-project funds; and
- (4)An estimate of the initial deposit, if any, and the estimated monthly deposit to the reserve for replacement account for the next 20 years.
- (b)Use of CNA. An owner may comply with paragraph (a) of this section by submitting a comprehensive needs assessment in accordance with title IV of the Housing and Community Development Act of 1992 (12 U.S.C. 1715z-1a note) if the CNA:
- (c)Reconsideration and modification of evaluation. If the PAE, after its independent review under § 401.451, determines that the owner's evaluation either fails to address specific necessary work items or fails to propose a cost-effective approach to rehabilitation, the owner may modify its evaluation to satisfy the concerns of the PAE.