- (a)In general. Recipients must initiate approved activities and projects promptly.
- (b)Construction activities. Recipients of funds for rehabilitation or new construction must meet the following standards:
- (1)Construction activities must begin within 9 months of the later of signing of the grant agreement or of signing an addendum to the grant agreement authorizing use of grant funds for the project.
- (2)Construction activities must be completed within 24 months of signing the grant agreement.
- (3)Activities that cannot begin until after construction activities are completed must begin within 3 months of the date that construction activities are completed.
- (c)Distribution. A recipient that receives funds through this part must:
- (1)Distribute the funds to subrecipients (in advance of expenditures by the subrecipients);
- (2)Distribute the appropriate portion of the funds to a subrecipient no later than 45 days after receiving an approvable request for such distribution from the subrecipient; and
- (3)Draw down funds at least once per quarter of the program year, after eligible activities commence.