Conversions to individually metered utility service shall be accomplished in the following order when a PHA has projects of two or more of the designated categories, unless the PHA has a justifiable reason to do otherwise, which shall be documented in its files.
- (a)In projects for which retail service is provided by the utility supplier and the PHA is paying all the individual utility bills, no benefit/cost analysis is necessary, and residents shall be billed directly after the PHA adopts revised payment schedules providing appropriate allowances for resident-supplied utilities.
- (b)In projects for which checkmeters have been installed but are not being utilized as the basis for determining utility charges to the residents, no benefit/cost analysis is necessary. The checkmeters shall be used as the basis for utility charges, and residents shall be surcharged for excess utility use.
- (c)Projects for which meter loops have been installed for utilization of checkmeters shall be analyzed both for the installation of checkmeters and for conversion to retail service.
- (d)Low- or medium-rise family units with a mastermeter system should be analyzed for both checkmetering and conversion to retail service, because of their large potential for energy savings.
- (e)Low- or medium-rise housing for the elderly should next be analyzed for both checkmetering and conversion to retail service, since the potential for energy saving is less than for family units.
- (f)Electric service under mastermeters for high-rise buildings, including projects for the elderly, should be analyzed for both use of retail service and of checkmeters.