- (a)Records retained according to the contract term. For each PBV project, the PHA must maintain the following records throughout the HAP contract term and for three years thereafter:
- (1)Records to document the basis for PHA selection of the proposal, if selection is competitive, or project, if selection is noncompetitive, including records of the PHA's site selection determination (see § 983.55) and records to document the completion of the review of the selection process in the case of PHA-owned units and copies of the written notice of proposal selection and response of the appropriate party;
- (2)The analysis of impact (see § 983.58(b)), if applicable;
- (3)The subsidy layering determination, if applicable;
- (4)The environmental review record, if applicable;
- (5)The Agreement to enter into HAP contract, if applicable;
- (6)Evidence of completion (see § 983.155), if applicable;
- (7)The HAP contract and any rider and/or amendments, including amendments to extend the term of the contract;
- (8)Records to document the basis for PHA determination and redetermination of rent to owner;
- (9)Records to document HUD approval of the independent entity or entities, in the case of PHA-owned units;
- (10)Records of the accessibility features of the project and each contract unit; and
- (11)Other records as HUD may require.
- (b)[Reserved]