24 CFR §990.180
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)General.
- (1)The rolling base consumption level (RBCL) shall be equal to the average of yearly consumption levels for the 36-month period ending on the June 30th that is 18 months prior to the first day of the applicable funding period.
- (2)The yearly consumption level is the actual amount of each utility consumed during a 12-month period ending June 30th. For example, for the funding period January 1, 2006, through December 31, 2006, the RBCL will be the average of the following yearly consumption levels:
- (b)Distortions to rolling base consumption level. The PHA shall have its RBCL determined so as not to distort the rolling base period in accordance with a method prescribed by HUD if:
- (1)A project has not been in operation during at least 12 months of the rolling base period;
- (2)A project enters or exits management after the rolling base period and prior to the end of the applicable funding period; or
- (3)A project has experienced a conversion from one energy source to another, switched from PHA-supplied to resident-purchased utilities during or after the rolling base period, or for any other reason that would cause the RBCL not to be comparable to the current year's consumption level.
- (c)Financial incentives. The three-year rolling base for all relevant utilities will be adjusted to reflect any financial incentives to the PHA to reduce consumption as described in § 990.185.