The Secretary has the following role regarding a construction program or project contained in a funding agreement or construction project agreement:
- (a)On a schedule negotiated by the Secretary and the Tribe/Consortium, to ensure health and safety standards and compliance with Federal law, the Secretary shall review and verify, to the satisfaction of the Secretary:
- (1)That project planning and documents prepared by the Tribe/Consortium in advance of initial construction are in conformity with the obligations of the Tribe/Consortium under 25 U.S.C. 5367(d); and
- (2)Before the project planning and design documents are implemented, that subsequent document amendments that result in a significant change in construction are in conformity with the obligations of the Tribe/Consortium under 25 U.S.C. 5367(d).
- (b)Where no time is otherwise specified in a funding agreement or construction project agreement, the Secretary shall complete the review and verification of project documents required under 25 U.S.C. 5367(h) and provide a Tribe/Consortium a written response within 30 days of the Secretary's receipt from the Tribe/Consortium of project planning and design documents. Absent a written response by the Secretary within the 30-day period, the project planning and design documents, or amendments to such documents, shall be deemed to be conformity with the Tribe's obligations under 25 U.S.C. 5367(d).
- (c)The Secretary must approve any proposed changes in the construction project that require;
- (d)A Tribe/Consortium may make immaterial changes to the performance period and make budget adjustments within available Federal funding without an amendment to the funding agreement or construction project agreement.
- (e)The Secretary may conduct onsite project oversight visits semiannually or on an alternate schedule agreed to by the Secretary and the Tribe/Consortium. The Secretary must provide the Tribe/Consortium with reasonable advance written notice to assist the Tribe/Consortium in coordinating the visit. The purpose of the visit is to review the progress under the construction project agreement or funding agreement. At the request of the Tribe/Consortium, the Secretary must provide the Tribe/Consortium a written site visit report;
- (f)Where the Secretary and the Tribe/Consortium share construction project or program activities, the Secretary and Tribe/Consortium shall provide for the exchange of information;
- (g)The Secretary may reassume the construction portion of a funding agreement or construction project agreement if the Secretary, in accordance with subpart M of this part, makes a written finding of: