  1. (a)When no public hearing for a TTP project is scheduled, the BIA, FHWA, or a Tribe must give adequate notice to the public before project activities are scheduled to begin. The notice should include:
    1. (1)Project location;
    2. (2)Type of improvement planned;
    3. (3)Dates and schedule for work;
    4. (4)Name and address where more information is available; and
    5. (5)Provisions for requesting a hearing.
  2. (b)If the work is not to be performed by the Tribe, BIA will send a copy of the notice to the affected Tribe.