The project package must include the following documentation, approved by the appropriate Public Authority, before the start of construction:
  1. (a)Plans, specifications, and estimates;
  2. (b)A Tribal resolution or other authorized document supporting the project;
  3. (c)Certification of compliance with the requirements of 25 CFR part 169, as well as any additional public taking documentation clearances, if applicable.
  4. (d)Required environmental, archeological, and cultural clearances; and
  5. (e)Identification of design exceptions if used in the plans.