25 CFR §170.460
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
The project package must include the following documentation, approved by the appropriate Public Authority, before the start of construction:
- (a)Plans, specifications, and estimates;
- (b)A Tribal resolution or other authorized document supporting the project;
- (c)Certification of compliance with the requirements of 25 CFR part 169, as well as any additional public taking documentation clearances, if applicable.
- (d)Required environmental, archeological, and cultural clearances; and
- (e)Identification of design exceptions if used in the plans.