Upon receiving a contract proposal, the approving official will:
- (a)Notify the applicant in writing that the contract proposal has been received, within 14 days after receiving the contract proposal.
- (b)Review the contract proposal for completeness and request, within 20 days after receiving the contract proposal, any additional information from the applicant which will be needed to reach a decision.
- (c)On receiving the contract proposal for operational support, make a formal written determination and findings supporting the need for such funds. In arriving at such a determination, the approving official must be assured that each local education agency has made a good faith effort in computing State and local contributions without regard to funds requested.
- (d)Assess the completed contract proposal to determine if the proposal is feasible and if the proposal complies with the appropriate requirements of the Johnson-O'Malley Act and this part.
- (e)Approve or disapprove the contract proposal after fully reviewing and assessing the application and any additional information submitted by the applicant.
- (f)Promptly notify the applicant in writing of the decision to approve or disapprove the contract proposal.
- (g)If the contract proposal is disapproved, the notice will give the reasons for disapproval and the applicant's right to appeal pursuant to subpart K of this part.