30 CFR §203.87
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
This report defines the development plan and capital requirements for the economic evaluation and must contain the following elements.
- (a)A description of the development concept (e.g., tension leg platform, fixed platform, floater type, subsea tieback, etc.) which includes:
- (b)An identification of planned wells which includes:
- (c)A description of the production system equipment which includes:
- (d)A discussion of any plans for multi-phase development which includes the conceptual basis for developing in phases and goals or milestones required for starting later phases.
- (e)A set of development scenarios consisting of activity timing and scale associated with each of up to three production profiles (conservative, most likely, optimistic) provided in the production report for your field (§ 203.88). Each development scenario and production profile must denote the likely events should the field size turn out to be within a range represented by one of the three segments of the field size distribution. If you send in fewer than three scenarios, you must explain why fewer scenarios are more efficient across the whole field size distribution.