You must do the following to decommission a pipeline in place:
- (a)Submit a pipeline decommissioning application in triplicate to the Regional Supervisor for approval. Your application must be accompanied by payment of the service fee listed in § 250.125. Your application must include the following information:
- (b)Pig the pipeline, unless the Regional Supervisor determines that pigging is not practical;
- (c)Flush the pipeline;
- (d)Fill the pipeline with seawater;
- (e)Cut and plug each end of the pipeline;
- (f)Bury each end of the pipeline at least 3 feet below the seafloor or cover each end with protective concrete mats, if required by the Regional Supervisor; and
- (g)Remove all pipeline valves and other fittings that could unduly interfere with other uses of the OCS.