30 CFR §250.1752
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Before removing a pipeline, you must:
- (a)Submit a pipeline removal application in triplicate to the Regional Supervisor for approval. Your application must be accompanied by payment of the service fee listed in § 250.125. Your application must include the following information:
- (1)Proposed removal procedures;
- (2)If the Regional Supervisor requires it, a description, including anchor pattern(s), of the vessel(s) you will use to remove the pipeline;
- (3)Length (feet) to be removed;
- (4)Length (feet) of the segment that will remain in place;
- (5)Plans for transportation of the removed pipe for disposal or salvage;
- (6)Plans to protect archaeological and sensitive biological features during removal operations, including a brief assessment of the environmental impacts of the removal operations and procedures and mitigation measures that you will take to minimize such impacts; and
- (7)Projected removal schedule and duration.
- (b)Pig the pipeline, unless the Regional Supervisor determines that pigging is not practical; and
- (c)Flush the pipeline.