30 CFR §250.177
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
If BSEE grants or directs a suspension under paragraph § 250.172(b), the Regional Supervisor may require you to:
- (a)Conduct a site-specific study.
- (1)The Regional Supervisor must approve or prescribe the scope for any site-specific study that you perform.
- (2)The study must evaluate the cause of the hazard, the potential damage, and the available mitigation measures.
- (3)You must pay for the study unless you request, and the Regional Supervisor agrees to arrange, payment by another party.
- (4)You must furnish copies and results of the study to the Regional Supervisor.
- (5)BSEE will make the results available to other interested parties and to the public.
- (6)The Regional Supervisor will use the results of the study and any other information that becomes available:
- (b)Submit a revised Exploration Plan (including any required mitigating measures);
- (c)Submit a revised Development and Production Plan (including any required mitigating measures); or
- (d)Submit a revised Development Operations Coordination Document according to 30 CFR part 550, subpart B.