You must notify the appropriate BSEE District Manager when you successfully complete or recomplete a well for production. You must:
  1. (a)Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.
  2. (b)Provide the following information in your notification:
    1. (1)Lessee or operator name;
    2. (2)Well number, lease number, and OCS area and block designations;
    3. (3)Date you placed the well on production (indicate whether or not this is first production on the lease);
    4. (4)Type of production; and