30 CFR §250.221
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)You must use the DWOP process for any project that meets any of the following criteria:
- (1)Is planned in water depths greater than 1000 ft;
- (2)Will use subsea tieback development technology, regardless of water depth; or
- (3)Will use any new or unusual technology for any drilling, completion, workover, intervention, injection, production, pipeline, platform, decommissioning, or abandonment project.
- (b)If you are unsure if your project will use subsea tieback development technology or new or unusual technology, contact the Regional Supervisor for guidance.