30 CFR §250.867
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)You must equip temporary quarters with all safety devices required by API RP 14C, Appendix C (incorporated by reference as specified in § 250.198). The District Manager must approve the safety system/safety devices associated with the temporary quarters prior to installation.
- (b)The District Manager may require you to install a temporary firewater system for temporary quarters in production processing areas or other classified areas.
- (c)Temporary equipment associated with the production process system, including equipment used for well testing and/or well clean-up, must be approved by the District Manager.
- (d)The District Manager must approve temporary generators that would require a change to the electrical one-line diagram in § 250.842(a).