30 CFR §285.636
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
You must notify BSEE in writing of the following events, within the time periods provided:
- (a)No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.
- (b)No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.
- (c)At least 7 days before commencing commercial operations.