- (a)Your Fabrication and Installation Report must describe how your facilities will be fabricated and installed in accordance with the design criteria identified in the Facility Design Report; your BOEM-approved SAP, COP, or GAP; and generally accepted industry standards and practices. Your Fabrication and Installation Report must demonstrate how your facilities will be fabricated and installed in a manner that conforms to your responsibilities listed in § 285.105(a). You must include the following items in your Fabrication and Installation Report:
- (b)You must submit your FIR to BSEE pursuant to § 285.110.
- (c)You must provide the location of records, as required in § 285.714(c).
- (d)If you are required to use a CVA, the FIR must include the following certification statement with accompanying justification: “The fabrication and installation of this structure has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices, the FDR, and the approved SAP, GAP, or COP, as applicable. The certified design and as-built plans and specifications will be on file at [provide location].”