- (a)You must submit a Project Modification or Repair Report to BSEE in which you certify that major repairs and major modifications of renewable energy structures and crucial components to a completed project conform to accepted engineering practices.
- (1)A “major repair” is a corrective action involving structural members affecting the structural integrity of all or a portion of the facility or substantial repair of a Critical Safety Systems and Equipment, including those identified in your FDR.
- (2)A “major modification” is an alteration involving structural members affecting the structural integrity of all or a portion of the facility or substantial alteration of Critical Safety Systems and Equipment, including those as identified in your FDR.
- (b)The report must also identify the location of all records pertaining to the major repairs or major modifications, as required in § 285.714(c).
- (c)If you are required to use a CVA, the report described in paragraph (a) of this section must include the following certification statement with accompanying justification: “The [major modification or major repair] of this [structure or Critical Safety Systems and Equipment] has been certified by a BSEE-approved CVA to be in accordance with accepted engineering practices, the FDR, and the approved SAP, GAP, or COP as applicable.”