30 CFR §285.710
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)To comply with § 285.708(a)(4), the CVA or project engineer must make periodic onsite inspections while installation is in progress and must, as appropriate, verify, witness, survey, or check the installation and commissioning of items required by this section.
- (b)The CVA or project engineer must verify, as appropriate, all of the following:
- (1)Loadout and initial flotation procedures;
- (2)Towing operation procedures to the specified location, including a review of the towing records;
- (3)Launching and uprighting activities;
- (4)Submergence activities;
- (5)Pile or anchor installations;
- (6)Installation of mooring, tendon, and tethering systems;
- (7)Final deck and component installations;
- (8)Installation at the locations set forth in your FDR(s) and FIR(s); and
- (9)Commissioning of Critical Safety Systems and Equipment.
- (c)For a fixed or floating facility, the CVA or project engineer must verify that proper procedures were used during the following:
- (d)For a floating facility, the CVA or project engineer must verify structural integrity, stability, and ballast, and that proper procedures were used during the following:
- (e)The CVA or project engineer must conduct an onsite inspection of the installed facility as approved in your CVA scope of work.
- (f)The CVA or project engineer must make periodic onsite inspections to witness the commissioning of Critical Safety Systems and Equipment in order to verify that:
- (g)The CVA or project engineer must spot-check the equipment, procedures, and recordkeeping as necessary to determine compliance with the applicable documents incorporated by reference and the regulations under this part.