30 CFR §585.200
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)A lease issued under this part grants the lessee the right, subject to obtaining the necessary approvals, including but not limited to those required under the FERC hydrokinetic licensing process, and complying with all provisions of this part, to occupy, and install and operate facilities on, a designated portion of the OCS for the purpose of conducting:
- (b)A lease issued under this part confers on the lessee the right to one or more project easements without further competition for the purpose of installing gathering, transmission, and distribution cables; pipelines; and appurtenances on the OCS as necessary for the full enjoyment of the lease.
- (c)A commercial lease issued under this part may be developed in phases, with BOEM approval as provided in § 585.238.