BOEM will consider the following criteria in deciding whether to renew a lease or grant:
- (a)Design life of existing technology.
- (b)Availability and feasibility of new technology.
- (c)Environmental and safety record of the lessee or grantee.
- (d)Operational and financial compliance record of the lessee or grantee.
- (e)Competitive interest and fair return considerations.
- (f)Effects of the lease or grant on generation capacity and reliability within the regional electrical distribution and transmission system.
- (g)Other relevant factors, as appropriate.