StacksVerified U.S. regulatory reference

30 CFR §585.600

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
  1. (a)You must submit a SAP, COP, or GAP and receive BOEM approval before you conduct activities on your lease or grant as set forth in the following table:
  2. (b)BOEM may waive certain types of information or analyses that you otherwise must provide in your proposed plan when you demonstrate that:
    1. (1)Sufficient applicable information or analysis is readily available to BOEM;
    2. (2)The coastal or marine resources that are the subject of the information requirement are not present or affected;
    3. (3)Other factors affect your ability to obtain or BOEM's need for the required information; or
    4. (4)Information is neither necessary nor required for a State to determine consistency with its coastal management program.