To request an Alternate Use RUE, you must submit to BOEM all of the following:
- (a)The name, address, email address, and phone number of an authorized representative.
- (b)A summary of the proposed activities for the use of an existing OCS facility, including:
- (1)The type of activities that would involve the use of the existing OCS facility;
- (2)A description of the existing OCS facility, including a map providing its location on the lease block;
- (3)The names of the owner of the existing OCS facility, the operator, the lessee, and any owner of operating rights on the lease at which the facility is located;
- (4)A description of additional structures or equipment that will be required to be located on or in the vicinity of the existing OCS facility in connection with the proposed activities;
- (5)A statement indicating whether any of the proposed activities are intended to occur before existing activities on the OCS facility have ceased; and
- (6)A statement describing how existing activities at the OCS facility will be affected if proposed activities are to occur at the same time as existing activities at the OCS facility.
- (c)A statement affirming that the proposed activities sought to be approved under this subpart are not otherwise authorized by other provisions in this subchapter or any other Federal law.
- (d)Evidence that you meet the requirements of § 586.107, as required by § 586.108.
- (e)The signatures of the applicant, the owner of the existing OCS facility, and the lessee of the area in which the existing facility is located.