30 CFR §7.104
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Test procedures.
- (1)Isolate and seal each segment of the intake system or exhaust system to allow pressurization.
- (2)Internally pressurize each segment of the intake system or exhaust system to four times the maximum pressure observed in each segment during the tests of § 7.100, or 150 psig ±5 psig, whichever is less. Maintain the pressure for a minimum of 10 seconds.
- (3)Following the pressure hold, the pressure shall be removed and the pressurizing agent removed from the intake system or exhaust system.
- (b)Acceptable performance.
- (1)The intake system or exhaust system, during pressurization, shall not exhibit—
- (2)Following removal of the pressurizing agent, the intake system or exhaust system shall not exhibit any—
- (i)Changes in fastening torque;
- (ii)Visible cracks in welds;
- (iii)Permanent deformation affecting the length or gap of any flame-arresting paths;
- (iv)Stretched or bent fastenings;
- (v)Damaged threads of parts affecting the explosion-proof integrity of the intake system or exhaust system; or
- (vi)Permanent distortion of any planar surface of the diesel power package exceeding 0.04-inches/linear foot.