33 CFR §127.008
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)An owner or operator intending to build a new LNG fuel facility, modify construction of any LNG fuel facility, or reactivate an inactive LNG fuel facility electing to complete an operational risk assessment (ORA) in lieu of a WSA as outlined in § 127.007, must submit an LOI and ORA to the COTP of the zone in which the LNG fuel facility is or will be located at least 1 year prior to the start of LNG transfer operations.
- (b)Each LOI must contain the information in § 127.007(c)(1) through (c)(5).
- (c)The owner or operator who submits an LOI under paragraph (a) of this section must notify the COTP in writing within 15 days of any of the following:
- (d)The ORA required by paragraph (a) must:
- (1)Be carried out in accordance with Chapter 7 of ISO/TS 18683 and Appendix D of DNVGL-RP-G105; or Chapter 19 of NFPA 59A (all incorporated by reference, see § 127.003); or other industry developed risk assessment method acceptable to the Office of Operating and Environmental Standards, Commandant (CG-OES); and
- (2)Consider possible factors affecting the ship/shore interface and port operations described in Section 6 of ISO 28460 (incorporated by reference, see § 127.003).