33 CFR §127.315
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
Before transferring LNG, the person in charge of shoreside transfer operations must—
- (a)Inspect the transfer piping and equipment to be used during the transfer and replace any worn or inoperable parts;
- (b)For each of the vessel's cargo tanks from which cargo will be transferred, note the pressure, temperature, and volume to ensure they are safe for transfer;
- (c)Review and agree with the person in charge of cargo transfer on the vessel to—
- (d)Ensure that transfer connections allow the vessel to move to the limits of its moorings without placing strain on the loading arm or transfer piping system;
- (e)Ensure that each part of the transfer system is aligned to allow the flow of LNG to the desired location;
- (f)Ensure that warning signs that warn that LNG is being transferred, are displayed;
- (g)Eliminate all ignition sources in the marine transfer area for LNG;
- (h)Ensure that personnel are on duty in accordance with the examined Operations Manual; and
- (i)Test the following to determine that they are operable: