- (a)The owner or operator of a tanker subject to this subpart shall include the requirements of this section in the Prince William Sound geographic-specific appendix required by subpart D of this part.
- (1)The response plan must include identification of an oil spill removal organization that shall—
- (i)Perform response activities;
- (ii)Provide oil spill removal and containment training, including training in the operation of prepositioned equipment, for personnel, including local residents and fishermen, from the following locations in Prince William Sound—
- (iii)Consist of sufficient numbers of trained personnel with the necessary technical skills to remove, to the maximum extent practicable, a worst case discharge or a discharge of 200,000 barrels of oil, whichever is greater;
- (iv)Provide a plan for training sufficient numbers of additional personnel to remove, to the maximum extent practicable, a worst case discharge or a discharge of 200,000 barrels of oil, whichever is greater; and
- (v)Address the responsibilities required in § 155.1035(d)(4).
- (2)The response plan must include exercise procedures that must—
- (i)Provide two exercises of the oil spill removal organization each year to ensure prepositioned equipment and trained personnel required under this subpart perform effectively;
- (ii)Provide for both announced and unannounced exercises; and
- (iii)Provide for exercises that test either the entire appendix or individual components.
- (3)The response plan must identify a testing, inspection, and certification program for the prepositioned response equipment required in § 155.1130 that must provide for—
- (i)Annual testing and equipment inspection in accordance with the manufacturer's recommended procedures, to include—
- (A)Start-up and running under load of all electrical motors, pumps, power packs, air compressors, internal combustion engines, and oil recovery devices; and
- (B)Removal of no less than one-third of required boom from storage annually, such that all boom will have been removed and examined within a period of 3 years;
- (ii)Records of equipment tests and inspection; and
- (iii)Use of an independent entity to certify that the equipment is on-site and in good operating condition and that required tests and inspections have been performed. The independent entity must have appropriate training and expertise to provide this certification.
- (i)Annual testing and equipment inspection in accordance with the manufacturer's recommended procedures, to include—
- (4)The response plan must identify and give the location of the prepositioned response equipment required in § 155.1130 including the make, model, and effective daily recovery rate of each oil recovery resource.
- (1)The response plan must include identification of an oil spill removal organization that shall—
- (b)The owner or operator shall submit to the COTP for approval, no later than September 30th of each calendar year, a schedule for the training and exercises required by the geographic-specific appendix for Prince William Sound for the following calendar year.
- (c)All records required by this section must be available for inspection by the Coast Guard and must be maintained for a period of 3 years.