34 CFR §222.195
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
The Secretary makes funds available to a grantee during a project period using the following procedure:
- (a)Upon final approval of the grant proposal, the Secretary authorizes a project period of up to 60 months based upon the nature of the grant proposal and the time needed to complete the project.
- (b)The Secretary then initially makes available to the grantee 10 percent of the total award amount.
- (c)After the grantee submits a copy of the emergency or modernization contract approved by the grantee's governing board, the Secretary makes available 80 percent of the total award amount to a grantee.
- (d)The Secretary makes available up to the remaining 10 percent of the total award amount to the grantee after the grantee submits a statement that—