34 CFR §463.755
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
The MOU, fully described in § 463.500, must contain the following information whether the local areas use either the local one-stop or the State funding method:
- (a)The period of time in which this infrastructure funding agreement is effective. This may be a different time period than the duration of the MOU.
- (b)Identification of an infrastructure and shared services budget that will be periodically reconciled against actual costs incurred and adjusted accordingly to ensure that it reflects a cost allocation methodology that demonstrates how infrastructure costs are charged to each partner in proportion to its use of the one-stop center and relative benefit received, and that complies with 2 CFR part 200 (or any corresponding similar regulation or ruling).
- (c)Identification of all one-stop partners, chief elected officials, and Local WDB participating in the infrastructure funding arrangement.
- (d)Steps the Local WDB, chief elected officials, and one-stop partners used to reach consensus or an assurance that the local area followed the guidance for the State funding process.
- (e)Description of the process to be used among partners to resolve issues during the MOU duration period when consensus cannot be reached.
- (f)Description of the periodic modification and review process to ensure equitable benefit among one-stop partners.