(RCS-DAEN-CWO-53) The Division Engineer will submit a consolidated annual report to reach HQDA (DAEN-CWO-R) WASH DC 20314 not later than 30 October. This requirement expires 30 October 1979. The report will contain the following:
- (a)Districts reporting.
- (b)Number assigned each contract.
- (c)Name of projects covered under each contract.
- (d)Number of man-hours of increased law enforcement services provided under each contract.
- (e)Total contract cost.
- (f)Cost per man-hour for each contract.
- (g)Corps of Engineers administrative or overhead costs associated with each contract.
- (h)Number of arrests and type of offense committed, i.e., assault, burglary, auto theft, etc.
- (i)The Division Engineers assessment of the effects of the contract law enforcement program and recommendation.