43 CFR §2091.5-5
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)
- (1)The filing of an application for a power project with the Federal Energy Regulatory Commission withdraws the lands covered by the application from the operation of the public land laws; however, the lands remain open to the location, lease or disposal of the mineral estate.
- (2)The issuance of a permit or license for a project by the Federal Energy Regulatory Commission withdraws the lands from the operation of the mining laws. (See part 3730).
- (b)Lands withdrawn under section 24 of the Federal Power Act remain withdrawn until the withdrawal is vacated and the lands opened by proper authority.
- (c)After a withdrawal has been vacated, the lands are opened to the operation of the public land laws by notation of the lands records to that effect.