43 CFR §3137.112
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)If you demonstrate to BLM that reasons beyond your control prevent you, despite reasonable diligence, from starting actual or constructive drilling, reworking, or completing operations, BLM will extend all committed NPR-A leases as if you were performing constructive or actual drilling or reworking operations. You are limited to two extensions under this section.
- (b)You must resume actual or constructive drilling or reworking operations when conditions permit. If you do not resume operations—
- (1)BLM will cancel the extension; and
- (2)The unit terminates (see § 3137.131 of this subpart).