43 CFR §3261.15
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
You may submit your completed and signed drilling permit application and complete drilling program and operations plan either together or separately.
- (a)If you submit them together and we approve your drilling permit, the approved drilling permit will authorize both the pad construction and the drilling and testing of the well.
- (b)If you submit the operations plan separately from the drilling permit application and program, you must:
- (1)Submit the operations plan before the drilling permit application and drilling program to allow BLM time to comply with National Environmental Policy Act (NEPA); and
- (2)Submit a completed and signed Sundry Notice for well pad and access road construction. Do not begin construction until we approve your Sundry Notice.