- (a)Persons conducting mining operations on the effective date of these regulations, who would be required to submit a plan of operations under § 3802.1-1 of this title, may continue operations but shall, within 60 days after the effective date of these regulations, submit a plan of operations. Upon a showing of good cause, the authorized officer shall grant an extension of time to submit a plan of operations not to exceed an additional 180 days.
- (b)Operations may continue according to the submitted plan of operations during its review unless the operator is notified otherwise by the authorized officer.
- (c)Upon approval of a plan of operations, mining operations shall be conducted in accordance with the approved plan.