All requests for assistance that meet the eligibility requirements in §§ 404.6 and 404.7 will be evaluated by applying the following prioritization criteria:
- (a)Whether there is an urgent and compelling need for a rural water supply project that would:
- (b)The extent to which a rural water supply project promotes and applies a regional or watershed perspective to water resources management as defined in § 404.2;
- (c)The financial need of the project sponsors for assistance with the planning, design, and construction of a rural water supply project, as demonstrated by readily available local and regional economic indicators;
- (d)The extent to which Reclamation is uniquely qualified to plan, design, and build the project;
- (e)Whether a rural water supply project helps meet applicable requirements established by law;
- (f)The extent to which a rural water supply project serves Indian tribes that have nonexistent or inadequate water systems;
- (g)The extent to which a rural water supply project is ineligible for comprehensive funding (sufficient to fully fund planning and construction of the entire project) through other assistance programs;
- (h)The extent to which a rural water supply project is identified as a priority by state, tribal or local governments;
- (i)Whether a rural water supply project incorporates an innovative approach that effectively addresses water supply problems and needs, either by applying new technology or by employing a creative administrative or cooperative solution; and
- (j)Other criteria that Reclamation deems appropriate.