When a sponsor finds it is not on track to meet its performance measures, the sponsor must develop a plan to get back on track or submit a request to AmeriCorps to amend its performance measures. AmeriCorps may limit when amendments to performance measure can be submitted, as well as limit the types of changes a sponsor can make to performance measures. The request must include all of the following:
  1. (a)Why the project is not on track to meet its performance requirements;
  2. (b)How the project has been tracking performance measures;
  3. (c)Evidence of corrective steps taken;
  4. (d)Any new proposed performance measures; and
  5. (e)A plan to ensure that the project will meet the new proposed measure(s).